Known Issue Status

Occurrence KNOWN ISSUE OCCURRING FROM RELEASE 1.3  
Change Management Issue JS-1281 - Getting issue details... STATUS  

Behavior

  • Passed Test Case
    • Starting Situation
      • A holidays.xml file is being included into a order for "non working days"
      •  order.xml and holiday.xml  are deploy in to the Jobscheduler
      • Jobscheduler read the order.xml and included file holidays.xml 
      • Jobscheduler suppress the job execution for dates defined as "non working days" in the holidays.xml
    • Action
      • Check JOC and right click on the order --> show start times --> submit
    • Behavior
      • Jobscheduler will show all dates jobs will be executed. Jobscheduler will supress execution for "non working days"
  • Failed Test Case
    • Starting Situation
      • A holidays.xml file is being included into a order for "non working days"
      • User apply changes into the holiday.xml and deploy it in to Jobscheduler.
      • Jobscheduler does not read CHANGES from the  holiday.xml file.
    • Action
      • Check JOC and right click on the order --> show start times --> submit
    • Behavior
      • The Jobscheduler will ignore the changes from holiday.xml file and will execute jobs on "not working days".
  • Explanation
    • Jobscheduler read new or changed job, job chain, order and schedule files as soon as they are deployed in the Jobscheduler live folder. Jobscheduler does not reload chnages done in the  included  files i.e. holidays.xml

Requirement

  • The order should consider a newly added job node at the top of the job chain and should execute accordingly 

Workaround

  • Solution 1: Update the order configuration
    • An updated order configuration file will force JobScheduler to reload the order configuration and to adjust the assignment of the initial state.
  • Solution 2: Use start and end nodes
    • We recommend that you use our /sos/jitl/JobChainStart start job as the first node in every job chain and our /sos/jitl/JobChainEnd end job as the last full node. These are dummy jobs without any function of their own. However, they are helpful for fixing orders or pre-/post-processing rules: changes to the names and/or order of states within a job chain do not require a change to the order.

 