prevent the execution of a job or an order at the last sunday of a month
<span style"color:#A52A2A">
I would like to know if there a way to prevent the execution of a job or an order at a specific day?
For example, a job or an order which runs every day of every month. But I would like to stop it the last Sunday of each month.
</span>
it is a little bit tricky to prevent the execution of a job or an order at the last sunday of the month, but it works:
_
<run_time> <weekdays> <day day="1 2 3 4 5 6"> <period single_start="13:00"/> </day> </weekdays> <monthdays> <weekday day="7" which="-1"> <period single_start="13:00"/> </weekday> <weekday day="7" which="-2"> <period single_start="13:00" when_holiday="ignore_holiday"/> </weekday> <weekday day="7" which="-3"> <period single_start="13:00" when_holiday="ignore_holiday"/> </weekday> <weekday day="7" which="-4"> <period single_start="13:00" when_holiday="ignore_holiday"/> </weekday> </monthdays> <holidays> <weekdays> <day day="7"/> </weekdays> </holidays> </run_time>
_
<span ih1. "specificday">
h2. prevent the execution of a job or an order at a specific monthday
<span style"color:#A52A2A">
How to run a job or an order every day but stop it the 15th of each month?
</span>
_
<run_time> <monthdays> <day day="1 2 3 4 5 6 7 8 9 10 11 12 13 14 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31"> <period single_start="13:00"/> </day> </monthdays> </run_time>
_
<span ih1. "holyday">
h2. stop a job or an order for a not predefined period
<span style"color:#A52A2A">
_How can I stop a job or an order for a specific period which is not defined previously?
_
Example: my order is a daily order. But on e.g. 2013-05-01 I have a maintenance on the machine. So I would like to stop one chain or all the chains.''
</span>
To prevent the execution of a job or an order at a specific (not predefined) day you can define a holidays file (./config/live/holiday.xml)
<holidays> <holiday date="2013-05-01"/> </holidays>
and include it into your job(s) and order(s) with
<run_time> <period single_start="12:00"/> <holidays > <include live_file="/holiday.xml"/> </holidays> </run_time>
If it is necessary to define a day for maintenance you have to put it into holiday.xml and it would take effect for all jobs using this file via live_file="/holiday.xml" (caution: you have to restart the scheduler if you have changed holiday.xml).