Prevent the execution of a job or an order
...
for the last sunday of a month
<span style"color:#A52A2A">
I would like to know if there a way to prevent the execution of a job or an order at a specific day?
For example, a job or an order which runs every day of every month. But I would like to stop it the last Sunday of each month.
</span>
it is a little bit tricky to prevent the execution of a job or an order at the last sunday of the month, but it works:
Code Block | ||||
---|---|---|---|---|
| ||||
<run_time> |
...
<weekdays> <day dahy="1 2 3 4 5 6"> <period single_start"13:00"/> |
...
</day> |
...
</weekdays> |
...
<monthdays> <weekday day="7" which"-1"> |
...
<period single_ |
...
star="13:00"/> |
...
</weekday> |
...
<weekday day="7" |
...
which="-2"> |
...
<period single_start="13:00" when_ |
...
holiday="ignore_holiday"/> |
...
</weekday> |
...
<weekday day="7" |
...
which="-3"> |
...
<period single_start="13:00" when_ |
...
holiday="ignore_holiday"/> |
...
</weekday> |
...
<weekday day="7" |
...
which="-4"> |
...
<period single_start="13:00" when_ |
...
holiday="ignore_holiday"/> |
...
</weekday> |
...
</monthdays> |
...
<holidays> <weekdays> <day day"7"/> |
...
</weekdays> |
...
</holidays> |
...
</run_time> |
<span ih1. "specificday">
h2. prevent the execution of a job or an order at a specific monthday
<span style"color:#A52A2A">
How to run a job or an order every day but stop it the 15th of each month?
</span>
<run_time>
<monthdays>
<day dah1. "1 2 3 4 5 6 7 8 9 10 11 12 13 14 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31">
<period single_start"13:00"/>
</day>
</monthdays>
</run_time>
<span ih1. "holyday">
h2. stop a job or an order for a not predefined period
<span style"color:#A52A2A">
_How can I stop a job or an order for a specific period which is not defined previously?
_
Example: my order is a daily order. But on e.g. 2013-05-01 I have a maintenance on the machine. So I would like to stop one chain or all the chains.''
</span>
To prevent the execution of a job or an order at a specific (not predefined) day you can define a holidays file (./config/live/holiday.xml)
No Format |
---|
<holidays>
<holiday dath1. "2013-05-01"/>
</holidays>
|
and include it into your job(s) and order(s) with
No Format |
---|
<run_time>
<period single_start"12:00"/>
<holidays >
<include live_filh1. "/holiday.xml"/>
</holidays>
</run_time>
|
...