At this point the Create Calendar modal window will look like this:
Now click on Submit to save the Calendar.
...
Then click on Add Frequency as shown in the screenshot to specify the Non-Working Days:
Now configure the Frequency for the National Holidays for 2017 - in this use case we will be using holidays from the United Kingdom and selecting all the days.
Click on Add Frequency to note the configuration and then change the Year to 2018 and again select all days. The modal window should now look like this:
Once Add Frequency is clicked for the 2018 holidays the window will appear as shown in the next screenshot:
Note the configuration by clicking the Close button and then click Submit in the Create Calendar window to save the configuration.
...
Once the Non-Working Day Calendar has been configured the Resources / Calendars folder should look similar to the following screenshot:
Assign the Calendars to the Order
...
For the purpose of this demonstration a second Order - order_cs - has been configured alongside the original Order - order_c - that was configured for the Managing Working Day Calendars use case.
Now click on the menu for the order_cs as shown and select Set Run-time.
Assign the wkg_day_hol_natmo-fr and nwkg_day_hol_nat Calendars by opening the relevant Assign Working Day Calendar and Assign Non-Working Day Calendar links in the Set Run-time modal window.
The Assign Non-Working Days Calendar link will open the following selection window:
After selecting each Calendar, click on the Apply button at the foot of the window (not shown in the screenshot) to note the configuration.
Once both Calendars have been selected the Set Run-time window should appear as shown below:
Now click on the Submit button at the foot of the Set Run-time window to save the configuration.
...
The Edit XML function in the Set Run-time window can be used to inspect and - if necessary edit - the configuration for each individual day as shown below. Note that in contrast to the configuration described in the Calendar Use Cases - Managing Working Day Calendars article, Non-Working Days can be readily identified as such in the XML.
In addition, the Show Assigned Calendars item in the Order's menu allows the assigned calendars to be checked.
...
Now configure a second Single Start Period starting at 21:00. After this has been done the Set Run-time window will appear as shown in the following screenshot:
Inspecting the Configuration with the Daily Plan
...