Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Screenshots updated

...

Info
titleConfiguration Tip

This The approach to Calendar configuration described above simplifies administration as individual Frequencies can be deleted from, edited and added to a Calendar without the necessity of a new Calendar having to be assigned to Jobs or Orders. For example, the National Holiday Frequency for 2017 can be deleted in January 2018, and the National Holiday Frequency for 2019 added in Autumn 2018.

...

Once both Calenders have been selected the Set Run-time window should appear as shown below:

Image Added

Now , click on the Submit button at the foot of the Set Run-time window to save the configuration.Image Removed

Inspecting the Configuration

...

The Show Daily Plan item in the menu for the order_cs Order can be used to show how the configuration described above comes together:

Image Modified

The screenshot shows the Monthly view for December 2017, with Christmas and Boxing Day (2nd Christmas Day) holidays clearly indicated:

...

This will open the Add Frequency : modal window then select the Recurring Days modal window tab as shown in the next screenshot:

...

After configuring a Recurring Days Frequency for for every 3rd day December 2017 as shown in the screenshot above, repeat this procedure for Every 3rd day for 2018, valid from the 1st January to the 31st of December. In both cases the Valid From date sets the point from which every third day is to be counted. Click on Close once both Restrictions have been set. This will return to the Set Run-time window, which will appear as shown in the next screenshot: 

Now click on Submit to save the configuration.

Effect of Period Settings and Restrictions

...