Individual Period starts are shown in the Monthly views and unspecified and excluded days are highlighted in the Yearly view as shown.
Restricting Job Starts
The situation where Jobs and Orders are not to run on every business - i.e. working - day can also be readily incorporated in this Calendar.
This section of the article describes how to extend the configuration so that the Order only runs on every 3rd working day, taking account of holidays and weekends.
Procedure
Re-open the Wkg Day - Mo-Fr Calender using the Edit Calendar menu item as shown below.
Select the Edit Frequency function (pencil icon) in the Update Calendar window as shown:
Now, in the Update Frequencies window select the Recurring Days tab and complete the fields as shown:
Click Add Frequency and the Frequency entry will be modified as shown in the screenshot above.
Now click on Close to return to the Set Run-time window.
The final configuration, if required, is to edit the Periods and specify the behavior On Holiday.
The default Suppress Execution setting can be seen in the following screenshot
Calculation starts with the 1st of January, which, with the 15th is a non-working day in the USA. Here the wrong values are calculated ....