- Download: final_chain_job_chain_history.zip
- Extract the archive to a folder in your JobScheduler installation named
./config/live
. - The archive will extract the files to a sub-folder
parallel_job_chain_control.
- Note that you can store the sample files in any folder you like.
Pattern
Flowchart |
---|
# order_A [shape="ellipse",label="Order A\n start time: Friday 08:00 ",fillcolor="violet"] # order_B [shape="ellipse",label="Order B\n start time: Friday 07:00 ",fillcolor="violet"] # order_Z [shape="ellipse",label="Order Z\n start time: Friday 15:00 ",fillcolor="violet"] job job_chain_1 [label="Job Chain 1\nhas no relevant dependencies",fillcolor="orange"] job_chain_2 [label="Job Chain 2\nis started by Job Chain 1",fillcolor="violet"] job_chain_3 [label="Job Chain 3\nis started by Job Chain 1",fillcolor="lightskyblue"] job_chain_4 [label="Job Chain 4\nis started by Job Chain 1",fillcolor="aquamarine"] job_chain_5 [label="Job Chain 5\nis started by Job Chain 1",fillcolor="orangered"] job_chain_6 [label="Job Chain 6\nis started by Job Chain 4",fillcolor="yellow"] split1 [label="Split 1", fillcolor="orange"] job1 [label="Job 1", fillcolor="orange"] job2 [label="Job 2", fillcolor="orange"] sync1 [label="Sync 1", fillcolor="orange"] job1_2 [label="Job 1.2", fillcolor="orange"] job3 [label="Job 3", fillcolor="violet"] job4 [label="Job 4", fillcolor="violet"] job5 [label="Job 5", fillcolor="lightskyblue"] job6 [label="Job 6", fillcolor="lightskyblue"] job7 [label="Job 7", fillcolor="aquamarine"] job8 [label="Job 8", fillcolor="aquamarine"] job9 [label="Job 9", fillcolor="aquamarine"] job10 [label="Job 10", fillcolor="orangered"] job11 [label="Job 11", fillcolor="orangered"] job12 [label="Job 12", fillcolor="orangered"] job13 [label="Job 13", fillcolor="yellow"] job_chain_1 -> split1 split1 -> job1 -> sync1 split1 -> job2 -> sync1 sync1 -> job1_2 job1 -> job_chain_2 -> job3 -> job4 job2 -> job_chain_3 -> job5 -> job6 job1_2 -> job_chain_4 -> job7 -> job8 -> job9 job1_2 -> job_chain_5 -> job10 -> job11 -> job12 job9 -> job_chain_6 -> job13 job12 -> job_chain_6 [arrowhead="normal", color="lightslategrey"] job4 -> job8 [arrowhead="normal", color="lightslategrey"] job4 -> job11 [arrowhead="normal", color="lightslategrey"] job6 -> job11 [arrowhead="normal", color="lightslategrey"] job12 -> job12 [arrowhead="normal", color="lightslategrey"] |
Implementation
Components
- The solution contains six job chains:
JobChain1
runsJob1
andJob2
in parallel.- On successful completion of
Job1
thenJobChain2
is run - On successful completion of
Job2
thenJobChain3
is run
- On successful completion of
JobChain2
runsJob3
andJob4
JobChain3
runsJob5
andJob6
JobChain4
runs after successful completion ofJobChain1
JobChain4
runsJob7
,Job8
,Job9
Job7
runs 1stJob8
runs onceJob7
andJob4
have run successfully
JobChain5
runs after successful completion ofJobChain1
JobChain5
runsJob10
,Job11
andJob12
Job10
runs 1stJob11
runs onceJob10
,Job4
andJob6
have run successfullyJob12
runs onceJob11
has completed successfully
JobChain6
runs onceJob9
andJob12
have completed successfully
...